House Design Stages: 5 Steps and How to Choose an Architect
House Design Stages: 5 Steps and How to Choose an Architect

House Design Stages: 5 Steps and How to Choose an Architect

If you know the house design stages in advance, you can plan your construction timeline and budget far more accurately.

Building a private house starts with an architectural design, and it is at this stage that you decide how comfortable, safe and economical the home will be for decades to come. In this article we explain what a full design package includes, what stages the work goes through, and how to choose an architect so that you avoid unnecessary costs and delays.

📌 To calculate the cost quickly, use the architectural design cost calculator.

1. What does an architectural design include?

  • Concept design: the shape of the house, the layout, the facade idea, 3D visualization
  • Architectural part: floor plans, sections, facades, door and window specifications
  • Structural part: foundation, columns, roofing and their calculations (essential in Georgia because of seismic activity)
  • Engineering systems: electrical, water supply and sewerage, heating and ventilation
  • Permit documentation for the building permit

2. Design stages

  1. Technical brief: how many rooms and floors, the budget, the specifics of the plot
  2. Site survey: topography and geology (the soil type determines the foundation)
  3. Concept sketch and 3D: changes are cheap here and expensive later
  4. Working design: detailed drawings for the builders
  5. Permit and author’s supervision during construction

3. How to choose an architect?

  • Look at their completed (built) projects, not just renders
  • Clarify what the price includes: architecture only, or also structures and engineering systems
  • Agree on the number of revisions and deadlines in writing
  • Ask about author’s supervision: many mistakes appear during construction

4. Common mistakes

  1. Building without a design based on a “craftsman’s experience”: reworking later costs more than the design would have
  2. Skipping the geological survey: a wrong foundation is the main cause of cracks in houses
  3. Not planning the utilities: heating and electrical systems end up being “squeezed in” wherever they happen to fit

5. How much do the design and construction cost?

The cost of the design depends mainly on the area and the complexity. For an exact figure, use the architectural design cost calculator, and for the full construction budget, the construction calculator and the cottage calculator. For the interior, see the design calculator.

House design stages

House design stages: a quick summary

  1. Brief and budget: what you want and how much you can spend
  2. Site survey: topography and geology
  3. Concept sketch and 3D: agreeing on the shape and layout
  4. Working design: architecture, structures, utilities
  5. Permit and supervision: starting construction and keeping control of it

A decision made at each stage is cheaper than the same decision at the next one. That is why you should go through the house design stages in order and not skip any. You can read more about the role of the architect here.

House design stages in detail: what happens at each one

Stage 1: Technical brief

This is the most important and the most often skipped step. Write down how many people will live in the house, how many bedrooms, bathrooms and workrooms you need, whether you want a garage, terrace, pool or basement, and what budget you have for construction. The more precise the brief, the fewer changes there will be later.

Stage 2: Site survey

A topographic survey shows the exact boundaries of the plot, its slope and differences in elevation. A geological survey determines the soil type, the groundwater level and the correct type of foundation. On a sloping plot or on clay soil, building without a geological survey risks cracks and settlement.

Stage 3: Concept sketch and 3D visualization

The architect offers you several options: the layout, the facade and the massing. A 3D model helps you imagine how the sun will fall into the rooms, how the house will look from the street and how it will fit into the terrain. At this stage, changes are free or almost free.

Stage 4: Working design

The working design is the builders’ “instruction manual”: floor plans with dimensions, sections, facades, details, door and window schedules, structural drawings (reinforcement, concrete grade) and engineering systems. A good working design rules out “improvisation” during construction.

Stage 5: Permit and supervision

With the design, you apply for a permit to the local Urban Development Service. Once construction begins, the architect’s author’s supervision ensures that the house is built exactly according to the design.

House shape and cost: what makes construction more expensive

  • Complex shape: many corners, bay windows and a multi-pitched roof increase material and labor costs
  • Large cantilevers and wide glass facades require a stronger structure
  • A basement and an underground garage increase the foundation cost by 20–30%
  • A sloping plot requires retaining walls and earthworks

A simple, compact shape is not only cheaper but also more energy efficient: less exterior surface and less heat loss.

An energy-efficient house at the design stage

Correct orientation (living room facing south), good thermal insulation, double or triple glazing and planned ventilation reduce heating and cooling costs for years. All of this is cheapest to include in the design itself. For air exchange, read our article on heat recovery ventilation, and calculate your heating costs with the heating calculator.

House design stages: checklist

  • ☐ Technical brief and budget
  • ☐ Topography and geology
  • ☐ Concept sketch and 3D, approved
  • ☐ Working design: architecture, structures, utilities
  • ☐ Cost estimate
  • ☐ Permit
  • ☐ Author’s supervision contract

House design stages and timelines

Stage Typical duration Result
Technical brief 1–2 weeks List of requirements, budget
Topography and geology 1–3 weeks Site plan, soil report
Concept sketch and 3D 2–4 weeks Layout, facade, visualization
Working design 4–8 weeks Full drawings and specifications
Permit 2–6 weeks Building permit

In total, the house design stages usually take 2–5 months. This time is not “lost”: a well-planned house is built faster and more cheaply.

10 questions to ask the architect at your first meeting

  1. What does the price include: architecture, structures, utilities?
  2. How many revisions are included at the concept stage?
  3. Who does the structural calculations?
  4. Is the preparation of the permit included?
  5. What is the timeline for each stage?
  6. Can I visit houses that have been built?
  7. Do you provide author’s supervision?
  8. Will you take energy efficiency into account?
  9. Will I receive a cost estimate?
  10. In what format will I receive the files (PDF, DWG)?

What documents you receive when the design is complete

  • A site plan showing the placement of the house on the plot
  • Floor plans with dimensions and areas
  • Facades and sections
  • Structural drawings and calculations
  • Diagrams for electrical, water supply and sewerage, heating and ventilation
  • Specifications for doors, windows and materials
  • 3D visualization

These documents are not needed only for construction: they will also be useful for a bank loan, insurance and a future sale.

House design stages and budget allocation

Of the total construction budget, design usually makes up a small share, but it determines how efficiently the rest of the money is spent. A typical breakdown: foundation and frame 30–40%, roof and facade 15–20%, utilities 15–20%, interior finishing 25–35%. Calculate the exact figures for your house with the construction calculator, or, if you are considering a timber house, with the cottage calculator. Properly completed house design stages show you this budget in advance and with accuracy.

A real example: how a family saved 15 000 GEL

For a 180 m² house, a family first bought a “ready-made” design that had been prepared for a different plot. The geological survey showed that their plot had weak soil and that a standard strip foundation would not work. The architect adapted the design: changed the foundation, simplified the roof shape and rearranged the rooms according to the sun. As a result, they avoided reworking the foundation during construction, and saved about 15 000 GEL thanks to the simpler roof.

📹 Video tips on construction and renovation: Datvale YouTube · 👍 News and discounts: Datvale Facebook

Frequently asked questions

How long does it take to prepare a design?

For a private house, usually 1–3 months: the concept sketch takes 2–4 weeks and the working design 4–8 weeks, depending on complexity.

Are structural calculations necessary?

Yes. Georgia is a seismically active region, and the structural part is the foundation of the house’s safety.

Can I use a ready-made (standard) design?

You can, but it has to be adapted to your plot, soil and building codes, which often requires additional work.

What is author’s supervision?

The architect periodically checks that construction is proceeding according to the design, and records any mistakes in good time.

×